lanier islands resort, legacy villas

Project Details:

Construct six 4500 sqft commercial guest room lake side cottages

  • Wood framing

  • Poured wall basements and concrete floors

  • Plumbing, HVAC, and electrical construction

  • Sound attenuating insulation

  • Drywall construction

  • Heavy rustic timber millwork

  • Hand lay Tennessee Field Stone rock veneer in a fitted mortar-less fit

  • Cedar tongue and groove ceilings

  • High-end exterior door and window installation

  • Mortise and tendon heavy timber truss ceiling installation

  • Hardwood floor installation

  • Slate tile installation

  • Carpet installation

  • Sprinkler system

  • Fire alarm system

  • Low voltage/data wiring

  • Paint/stain throughout

  • Cabinets construction

  • Project duration: 10 months

Challenges:

  • Labor and material coordination to accomplish the work of six buildings within the construction timeframe of one

  • Logistically coordinate labor and materials with limited road access to that of a planned golf cart drive

  • Blind the construction site and activities to that of resort guests

  • Constructing poured in place large concrete fireplace caps (50’+ elevation) due to lack of crane spacing

  • Resort remained in operation throughout construction

  • Limited work hours, including mid-day and mid-week starts and stops to maintain conducive atmosphere to resort guests.